About the project
As part of our ongoing essential highway maintenance Infrastructure and Environment (IE) will undertake work along Route des Issues in St John.
The project will consist of patching sections of the existing carriageway where existing defects have been identified before the surface treatment work takes place.
The advance patching work should take 3 weeks and the surface treatment should take 4 weeks.
Map of works area for Route des Issues
Working hours and traffic management
As the project develops more information will be provided.
4 March to 15 March 2024 | Advance patching | Road closures 7:30am to 6pm Monday to Friday |
---|
May to June 2024 | Surface treatment | Road closures 7:30am to 6pm Monday to Friday
|
---|
Diversion routes
Map of diversion route for Route des Issues works
Westbound
La Rue Millitaire, La Route du Mont Mado, La Rue des Issues.
Eastbound
La Rue des Issues, La Route du Mont Mado, La Rue Millitaire.
Access
Access to all businesses and premises will be maintained where possible during the works.
Buses
Find more information relating to changes to the bus service on
LibertyBus.