Energy from Waste incinerator emissions testing (FOI)

Energy from Waste incinerator emissions testing (FOI)

Produced by the Freedom of Information office
Authored by States of Jersey and published on 17 December 2018.

Request

With regard to the eight monitored items on the La Collette chimney from the Incinerator;

  • Hydrogen Chloride

  • Sulphur Dioxide

  • Nitrous Oxides

  • Carbon Monoxide

  • Particulates

  • Volatile Organic Compounds

  • Carbon Dioxide

  • Moisture Content

Can you send me a schedule of the results of the tests and calibrations done twice yearly for the last ten years by the independent analysts and any comments from the Environment Department regulator made regarding these results?

Response

Detailed below is a schedule of the results of the tests and calibrations undertaken to date. We are not able to supply a schedule of the results of the tests and calibrations done twice yearly for the last ten years as the Facility was not processing waste until 2011.

The results are based on the test procedures in the Environment Agency’s Performance Standards and Test Procedures for Continuous Emission Monitoring Systems (CEMS) and Transportable-CEMS (T-CEMS) which is published information available at the following link:

Performance Standards and Test Procedures

 

​ ​Schedule of the results of the tests and calibrations

​Year

​Result

​2011 - test 1 ​Pass
​2011 - test 2​Pass
​2012 - test 1​Pass
​2012 - test 2​Pass
​2013 - test 1​Pass
​2013 - test 2​Pass
​2014 - test 1​Pass
​2014 - test 2​Pass
​2015 - test 1​Pass
​2015 - test 2​Pass
​2016 - test 1​Pass
​2016 - test 2​Pass
​2017 - test 1​Pass
​2017 - test 2​Pass
​2018 - test 1​Pass
​2018 - test 2​Pass

 

The incinerator emissions are published on our website and can be found at the web address below.

Energy Recovery Facility

The Environment Department regulator has not made any specific comments regarding these results as the plant is compliant with the Waste Incineration Directive and is in compliance with the Waste Management Licence which controls the operation of the Facility.