Site asbestos register and management plan for the engineering hangar at Jersey Airport (FOI)Site asbestos register and management plan for the engineering hangar at Jersey Airport (FOI)
Produced by the Freedom of Information officeAuthored by States of Jersey and published on
20 August 2015.Prepared internally, no external costs.
Request
A.
The date from which the site asbestos register and management plan for the hangar came into effect; and
B.
Details of the parts of the infrastructure that have / still contain asbestos;
C.
Please may I have a copy of the register and the management plan?
Response
A.
The asbestos management plan and register came into effect in its current form on the 24/09/2008.
B.
In summary:-
- AIB and paper clad ceiling tiles in the engineering hanger. Tiles of both varieties to be found only in both side extensions to the main hangar
- side and roof cladding sheets, guttering, rainwater goods and other profiled sheets
- rope to batens sealing windows to side extensions of main hanger. More clarity and detail is available in the main report below
C.
Find the Asbestos Register and Management Plan for the engineering hangar at Jersey Airport below.
Download site asbestos register and management plan (size 3.35mb)