TREASURY AND RESOURCES MINISTER
housing - capital budget transfer request:
le geyt flats refurbishment
1. Purpose of Report
1.1. The Minister for Treasury and Resources is asked to consider a request of the Minister for Housing to transfer unspent budget sums totalling some £390,000 from various completed Housing Departments capital works to fund refurbishment works on 21 flats within the redbrick building at Le Geyt Flats, St Saviour.
2. Background
2.1. The Treasury has recently undertaken an exercise across all departments to close down completed capital works that were still showing as work in progress.
2.2. The exercise in the Housing Department identified an unspent balance of £471,931 - £449,934 of which resulted from underspends on the Le Geyt redevelopment phases 4 - 6. Of this, £83,039 will be required to meet costs incurred on other Housing Departments projects, leaving an available balance of £388,892.
2.3. The former Housing Committee, in its Act B14 of 28 October 2005, identified an urgent need to modernise the ‘red brick’ building at Le Geyt.
2.4. The Housing Department estimates the cost of the proposed works in the order of £350,000, for which there is no other readily available source of funding.
3. Comments
3.1. The default position for unspent capital budget sums is that the value is returned to the Consolidated Fund.
3.2. Financial Direction 3.6 ‘Variations to Heads of Expenditure’ permits the transfer of capital budgets from one expenditure head to another, subject to the approval of the Minister for Treasury and Resources.
3.3. Such approval is delegated to the Treasurer for non-contentious items up to £100,000.
3.4. The Housing Department is proposing a refurbishment programme comprising:
· New roof;
· New windows;
· New doors - both communal and individual flats, with a security system;
· Overcladding to counter water penetration and improve insulation;
· New floor coverings;
· Improvements to communal areas.
3.5. The cost estimate is based on a tendering exercise undertaken in 2003 that did not progress due to lack of funds. The estimate of £350,000 allows for inflation over the intervening period.
3.6. Should the Minister approve the funding transfer and the cost of the proposed refurbishment be less than the transferred sum, any balance will be returned to the Consolidated Fund.
4. Recommendation
4.1. That the Minister for Treasury and Resources approves the proposed budget transfer.
5. Reasons for Decision
5.1. The Housing Department considers the refurbishment work to be of a high priority.
5.2. Proposition P211/2005, considered by the former Finance and Economics Committee at its meeting of 22 September 2005, identifies the requirement within the listing produced as ‘Appendix B’. That proposition is yet to be debated by the States, but there has been a general acknowledgement that investment in some areas of existing States social housing is a high priority.
5.3. The majority of the unspent funds were originally allocated for the phased development of the Le Geyt estate and the proposed refurbishment may be considered as a continuation of the rolling refurbishment programme.
States Treasury Corporate Finance
2 February, 2006 for Decision Meeting 30/01/2006