St. Peter's Valley: Path: Site Works Approval

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 3 September 2015:

Decision Reference:  MD-T-2015-0064

Decision Summary Title :

Valley Path, St Peter’s Valley

Date of Decision Summary:

28 August 2015

Decision Summary Author:

 

Director of Engineering and Infrastructure

Decision Summary:

Public or Exempt?

 

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Valley Path, St Peter’s Valley

Date of Written Report:

28 August 2015

Written Report Author:

Director of Engineering and Infrastructure

Written Report :

Public or Exempt?

 

Exempt

QE Article 33(b)

Subject:  Valley Path, St Peter’s Valley

 

Decision(s):  The Minister approved site works for the Valley Path project to commence in October 2015 subject to Planning Permission being granted and all necessary land transactions being in place.

 

Reason(s) for Decision:  To confirm the Minister’s approval of the scheme and allow enabling and pre construction works to commence.

 

Resource Implications:  Funding for the scheme is available in existing and proposed TTS budgets and will be supplemented from the Planning Obligation Agreement with Granite Products. 

 

Action required:  Director of Engineering and Infrastructure to instruct Jersey Property Holdings to prepare in principle Ministerial Decisions for the first tranche of the land transfers.

 

Signature:

 

 

Position:

Minister for Transport and Technical Services

 

Date Signed:

 

 

Date of Decision (If different from Date Signed):

 

 

Back to top