Jersey Harbours: Capital Budget Transfer

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made on 15 October 2010 regarding a capital budget transfer within Jersey Harbours

Decision Reference:  MD-E-2010-0158

Decision Summary Title:

DS – Jersey Harbours – Capital Budget Variation  (XY0905 & XY1008)

Date of Decision Summary:

22 September 2010

Decision Summary Author:

Director of Finance & Business Resources

Decision Summary:

Public or Exempt?

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title:

WR –Variation to capital budgets (XY0905 &XY1008)

Date of Written Report:

22 September 2010

Written Report Author:

Director of Finance & Business Resources

Written Report :

Public or Exempt?

Public

Subject

Capital budget transfer within Jersey Harbours

Decision(s):

The Assistant Minister approved the transfer of £150,000 from Civil Remediations (XY0905) to Elizabeth Harbour E.Pier project (XY1008)

Reason(s) for Decision:

The Elizabeth East Pier Project was originally approved for 2013 in the 2010 Business Plan. Subsequent investigations meant that it was necessary to bring the project forward to 2010 and a Ministerial Decision was approved to this effect (MD-TR-2010-00091). The costs of these investigations have been posted to XY0905. As a separately identifiable budget has now been approved for this project it would seem appropriate the transfer the costs and equivalent budget from XY0905 to the XY1008 to aid in transparency of costs and a clear audit trail upon transfer to fixed assets at conclusion of the project.

Resource Implications:

None

Action required:

For the Finance Director to seek the Treasurer of the States approval for the transfer. Once approval is obtained, the Finance Director to action budget transfers.

Signature:

Position:

Assistant Minister – Economic Development

Date Signed:

Date of Decision:

Jersey Harbours: Capital Budget Transfer

PUBLIC REPORT  

Report Name: Variation of Capital Budget (XY0905 & XY1008)    

Support for Ministerial Decision – Transfer of capital budget between Civil Remediations (XY0905) to Elizabeth Harbour E.Pier (XY1008)) – Economic Development Department – Jersey Harbours  

Date:  22/09/2010 

Purpose of Report  

To approve the transfer of £150,000 from Civil Remediations (XY0905) to the Elizabeth Harbour, E.Pier capital project (XY1008) to allocate investigative and design fees to the specific project to which they relate. 

Background  

The States of Jersey have already approved capital allocations for 2010 in the 2010 Business Plan. The Elizabeth East Pier Project was originally approved for 2013 in the 2010 Business Plan. Subsequent investigations meant that it was necessary to bring the project forward to 2010 and a Ministerial Decision was approved to this effect (MD-TR-2010-00091). 

As outlined in the report for MD-TR-2010-00091;The site investigations involved diver inspection of all foundations of the East Pier followed up by laboratory analysis of the concrete samples taken from the foundations. It is evident that Pier No 3 has undergone serious undermining due to scouring from Ferry movements with No 2 and No 4 suffering moderate scour damage. Laboratory testing has shown that the concrete is within specification. The scour damage will need to be rectified to ensure continued safe operation of the pier.  

The costs of these investigations have been posted to XY0905. As a separately identifiable budget has now been approved for this project it would seem appropriate the transfer the costs and equivalent budget from XY0905 to the XY1008 to aid in transparency of costs and a clear audit trail upon transfer to fixed assets at conclusion of the project. 

The following table identifies the effect of transfers between Jersey Harbours capital projects as a result of this decision. 

 

Capital Budget at 1st January 2010 
 
 
 

£

Transfers (to)/from Jersey Harbours Trading Fund

(MD-TR-2010-00091)

£

Proposed transfer between heads of capital expenditure 
 

£

Re-stated Capital Budgets after transfer between head of capital expenditure

£

Civil Remediations

350,000

 

(150,000)

200,000

Elizabeth Harbour, E.Pier

0

300,000

150,000

450,000

 

 

 

 

 

 
 
 

Recommendations 

To approve the transfer of £150,000 budget from Civil Remediations (XY0905) to the Elizabeth Harbour, E.Pier capital project (XY1008).

 