Future Hospital project costs (FOI)

Future Hospital project costs (FOI)

Produced by the Freedom of Information office
Authored by States of Jersey and published on 26 January 2018.

Request

Please can you tell me how much has been spent on the new hospital project to date? Including consultation fees, planning application costs and any other areas of States of Jersey spending on the development.

Please could this be presented as a breakdown of the different areas?

Response

From the commencement of the “Future Hospital” project in October 2012 until 31 December 2017, costs totalling £24,569,182 have been incurred. These costs can be summarised as follows:

​Summary costs​£
​Pre-feasibility and feasibility work​576,525
​Internal client costs​1,773,588
​External advisors ​13,477,857
​Stakeholder engagement​157,275
​Property  ​235,661
​Offsite preliminary works​5,989,060
​Site acquisition​397,710
​Relocation works  ​1,749,256
​Planning fees​212,250
​Total expenditure to 31 December 2017​24,569,182

 