Maternity Ward refurbishment (FOI)Maternity Ward refurbishment (FOI)
Produced by the Freedom of Information officeAuthored by Government of Jersey and published on
21 February 2022.Prepared internally, no external costs.
Request
A
Please could you tell me the plan and indicative timescales for each individual phase of the maternity ward refurbishment, due for completion in October 2023?
B
Please could you also confirm when the current noise disruption as part of the refurbishment is expected to be finished by May 2022?
Response
A
Enabling Works | Late July 2021 | Mid August 2021 |
Phase 1 New Bereavement Suite, Learning and Development Room and HDU with Donning and Doffing Facility | August 2021 | Due to be presented back on 14 February 2022 |
Phase 2 | February 2022 | April 2022 |
Phase 3 | April 2022 | June 2022 |
Phase 4 | June 2022 | August 2022 |
Phase 5 | August 2022 | October 2022 |
Phase 6 Now consolidated with Phase 2 | October 2022 | December 2022 |
Phase 7 | December 2022 | February 2023 |
Phase 8 | February 2023 | April 2023 |
Phase 9 | April 2023 | July 2023 |
Phase 10 | June 2023 | August 2023 |
Phase 11 | August 2023 | October 2023
|
B
Phase 2 and 6, which will deliver a new SCBU and staff change area and office space, are being joined together in order to diminish disruption to babies in SCBU and expedite project completion.