Maternity Ward refurbishment (FOI)

Maternity Ward refurbishment (FOI)

Produced by the Freedom of Information office
Authored by Government of Jersey and published on 21 February 2022.
Prepared internally, no external costs.

Request

A

Please could you tell me the plan and indicative timescales for each individual phase of the maternity ward refurbishment, due for completion in October 2023?

B

Please could you also confirm when the current noise disruption as part of the refurbishment is expected to be finished by May 2022?

Response

A

Phase

Anticipated Start

Anticipated Completion

Enabling Works

Late July 2021

Mid August 2021

Phase 1

New Bereavement Suite, Learning and Development Room and HDU with Donning and Doffing Facility

August 2021

Due to be presented back on 14 February 2022

Phase 2

February 2022

April 2022

Phase 3

April 2022

June 2022

Phase 4

June 2022

August 2022

Phase 5

August 2022

October 2022

Phase 6

Now consolidated with Phase 2

October 2022

December 2022

Phase 7

December 2022

February 2023

Phase 8

February 2023

April 2023

Phase 9

April 2023

July 2023

Phase 10

June 2023

August 2023

Phase 11

August 2023

October 2023


B

Phase 2 and 6, which will deliver a new SCBU and staff change area and office space, are being joined together in order to diminish disruption to babies in SCBU and expedite project completion.