Please provide the following details about the explosion site at Haut du Mont, Pier Road:-
A
When was the Haut du Mont site returned to the Government of Jersey following the end of the States of Jersey Police's investigation of the site?
B
Which security company has been employed to provide round the clock security of the site?
C
Since the security company have been operating at the site on behalf of the Government of Jerey, how much has it cost to have it in place?
d
How long is their contract expected to last?
Response
A
The Government of Jersey assumed responsibility for the ‘outer’ cordon in March 2023; that responsibility will effectively be discharged by G4S. Andium assumed responsibility for the ‘inner’ cordon.
The outer cordon is the perimeter of the site and access into the site. The inner cordon is access to the buildings and structures.
B
G4S.
C
£457,574.40 (for 12 months).
D
The current contract is for 12 months, however, rolling depending on the needs of the site.