TRANSPORT AND TECHNICAL SERVICES
BELLOZANNE SEWAGE TREATMENT WORKS – CONSENT COMPLIANCE
Purpose of the Report
The purpose of the report is to brief the Minister on the Bellozanne Sewage Treatment Works consent compliance works that are currently being undertaken. It outlines the drivers for the proposed works, their scope and the capital cost.
Discussion
In the early 1990s, it became evident that the Sewage Treatment Works needed to be upgraded to increase its capacity and replace some of the outdated/inefficient equipment. Subsequently, it was agreed that the upgrade should include a nutrient removal process to decrease the amount of nitrogen entering St Aubin’s Bay.
The work was completed in 2002 but the agreed nitrogen output levels were not met. The discharge permit (reference number DC2000/07/01) under the Water Pollution (Jersey) Law, 2000 requires an annual average concentration of less than 10 mg/l total nitrogen and 35 mg/l suspended solids (on a 95 percentile basis).
The Department has continued with its efforts to improve the performance of the works together with monitoring of the water quality in St Aubin’s Bay. The Process Optimisation Study concluded that Activated Sludge Plant (ASP) is undersized for the present and future conditions, and will not achieve the nitrogen limit. The performance of the works is and has always been adversely affected by the limited hydraulic gradient. Flow distribution at each stage of the process is unsatisfactory.
The study identified a number of short to medium term options to address some of the shortcomings. Others can be rectified in time, perhaps by adopting a phased approach. Regardless of the approach, it is important that all works fit in with the long term plans for sewage treatment in Jersey.
This briefing provides an update on the current status of the investigations and works to improve the performance of the ASP. The main items of work are described in the following table.
Issue Description | Proposed Solution | Current Status |
1. Eradicate the filaments for improved settleability and overcome foaming problems | Modify the ‘selectors’ at the start of the activated sludge process | Implemented in 2009 at a cost of £100k |
2.Improve the plug flow arrangements and reduce short circuiting in the lanes. | Provide baffles in the anoxic zones | Included in above |
3. Improve the security of the system and allow for process variations | Provide RAS pumps and associated equipment | See following text |
4. Need for a more robust system for improved reliability | Investigate process options | See following text |
5&6. Effective denitrification | Establish the mixed liquor recycles/ use of a carbon source | See following text |
7. Negotiate relaxed consent with the Regulator | Carry out Eutrophic Status study of St Aubin’s Bay to determine if the receiving waters are capable of taking more nitrogen | Survey ongoing. Due to finish in July 2010 |
8. New discharge permit conditions required by the Regulator | Installation of measured applied dose monitoring in UV plant required. | Awaiting quotations |
Item 3 & 4 Return Activated Sludge (RAS) Pumping Station
The existing RAS Pumping Station has two Archimedes screw pumps (duty/assist, each rated 325 l/s) with no standby capacity. It is proposed to construct a new submersible pumping station with two pumps (duty/assist, each rated 200 l/s). One of the existing RAS screw pumps would be retained as standby. The delivery main will include a bifurcation to enable the RAS to be delivered to the front and/or the back end of the selector zones of each lane.
On completion of these items, Item 5 will be brought back into service and Item 6 will be initiated as part of continuous improvements.
Items 5 & 6 Process Options
All ASP options must meet the total nitrogen consent and to facilitate this, nitrification and denitrification processes are required.
Denitrification
This requires recycling of the mixed liquor, which is the discharge from the aeration tanks. As noted previously, recycling presently exacerbates the filament problem, there are associated foaming problems and the process becomes unstable. Some temporary works have been completed to stabilise the process and permit recycling.
Nitrification
To achieve full nitrification, the 2002 upgrade incorporated Pegazur pellets in the aeration zones. This is a high rate fixed film process which requires a far smaller footprint than a conventional plant. These pellets are no longer readily available and due to the loss of these pellets by natural abrasion, those in Lane 3 were used to top up the other cells and replaced with Meteor pellets. However, these only work well with coarse bubble diffusers and not the fine bubble diffuser system in Bellozanne. This is because the biological film on the pellets is removed by the scouring action by the fine bubbles.
A number of other options have been investigated, which cover a range of processes and prices. Replacing the Meteor pellets with Pegazur ones might result in full nitrification. However, because of the ongoing reduction in pellets, there will probably be a need to top them up in a few years time at significant cost. The only manufacturer is in Japan and they will not offer any process guarantees.
Eimco Water Technologies have suggested a low cost solution based on the IFAS (Integrated Fixed Film Activated Sludge) Cleartec Process. Eimco has indicated that full nitrification can be achieved within the aeration zones and it will be a requirement for the supplier to provide a performance guarantee. However, due to inadequate anoxic zone volume, it will not be possible to guarantee the annual average total nitrogen level without the addition of an external carbon source. As an alternative, Eimco are to explore the possibility of managing the return liquor load.
Although the process is attractive and has a number of intrinsic benefits, there are some risks. Therefore, it is proposed to undertake a performance trial in Lane 3 prior to full installation. Trial procedures have been agreed to assess the performance of the process.
A breakdown of the cost is as follows:
Lane 3 Upgrades in Year 2010 £ 545,000.00
Lane 2 Upgrades in Year 2011 £ 500,000.00
Lane 1 Upgrades in Year 2012 £ 500,000.00
Total £1,545,000.00
The implementation of the ASP trial at the earliest opportunity would demonstrate to the Regulator that positive steps are being taken, thereby minimising the risk of prosecution. The estimated total project cost of this is £1,545,000, with the initial cost to complete the works in Lane 3 being £545,000. Further investigations will be carried out on the use of a carbon source in the anoxic zone. In the meantime, it will be necessary to apply for interim discharge consent for a higher total nitrogen limit. This will only be possible once the results from the St Aubin’s Bay Eutrophic Status study are available.
Recommendations
The Minister is recommended to note the progress on the Bellozanne Sewage Treatment Consent Compliance Projects.
Reason (s) for Decision
The Sewage Treatment Works is currently failing its discharge permit under the Water Pollution (Jersey) Law, 2000. Completion of the project will enhance the current performance of the sewage treatment works reducing nitrogen inputs into receiving waters.
Action Required
N/A
| |
Written by: | Senior Operations Manager – Waste Water Treatment |
| |
Approved by: | Acting Waste Director |