St. Martin's School: New School and Nursery: Approval of Drawings and Tender Acceptance

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 17 July 2013:

Decision Reference: MD-PH-2013-0110

 

Decision Summary Title :

St Martin’s School & Nursery- Approval of Drawings and Acceptance of Tender

Date of Decision Summary:

09 July 2013

Decision Summary Author:

 

Head of Capital, Jersey Property Holdings

Decision Summary:

Public or Exempt?

 

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Approval of Drawings and Acceptance of Tender Report

Date of Written Report:

09 July 2013

Written Report Author:

Head of Capital, Jersey Property Holdings

Written Report :

Public or Exempt?

 

WR and SD

Exempt 3.2 (a) (x)

Subject: St Martin’s School - Approval of Drawings and Acceptance of Tender for New School and Nursery.

Decision(s):

 

(a)     In accordance with paragraph 1 (d) of Standing Order 168, the Minister accepts the Planning approved Building Permit No. B/2012/1116 and drawings numbered:

 10219:100, 101, 102, 103, 104, 105, 106, 107, 108, 109, 110, 111, 112, 113, 114, 115, 116, 117, 118, 119, 120; JY12013:200, and EPG/7818/SD/01 - all showing the proposed works to construct the New Single Entry Primary School and Nursery at St Martin.

 

(b)     The Minister agreed to accept the 74 week preferred fix price tender and enter into a formal “JCT Standard Form1980 “ with JF Marett & Son Ltd  in the tendered sum of £5,229,750.00 and delegated the Director of Property Holdings to conclude the final contract arrangements within the available budget.

Reason(s) for Decision:

 

The drawings noted in item (a) above and which bye-law approval have been granted (Permit No. B/2012/1116 refers) reflect the use for which the funding is provided.

 

Under Standing Order 168 (1) (d), it is a requirement for the Minister for Treasury and Resources to approve plans for the construction (or alteration) of buildings where the work is to be funded wholly or partly by money voted by the States.

 

The estimated total cost for the works at St Martin’s School (including the tender accepted, professional fees and ‘other’ costs), as designed, can be completed within the allocated budget.

 

The preferred fix price tender submitted by JF Marett & Son Ltd can be accepted and a contract entered into.

Resource Implications:

 

Other than those noted in the report, there are no further financial or manpower implications.

Action required:

 

The Director of Jersey Property Holdings to sign the contract and any other associated documentation.

Signature:

 

 

Position:

Senator Philip Ozouf,

Minister  for Treasury and Resources

 

 

Date Signed:

 

 

Date of Decision (If different from Date Signed):

 

 