Schemes which are Planned, Funded and Programmed for 2007 |
Date | Scheme | Comments | Cost |
2007 | Jambart Lane. Pedestrian footpath improvements to Jambart Lane following consultation on Cat A site, and continuing consultation with Parish and residents. | Contribution of £37,500 from developer of cat A housing site. Should cover cost however promise from previous E&PSC President to top up developer contribution if required. | £0 |
2007 | Mont Cochon Traffic Calming Minor alterations and traffic calming to control speed on one-way section following traffic management | Programmed to be on site in July. | £15,000 |
2007 | Plat Douet/ Green Road Routine signal replacement and upgrade of pedestrian facilities | Signals need replacement. Pedestrian upgrade in line with current policy established by previous E&PSC. | £15,000 Civils £10,000 Signals |
2007 | Route du Fort/ St Clements Road Signals Routine signal replacement and upgrade of pedestrian facilities | Signal equipment due for replacement. Limited pedestrian upgrade. | £22,000 Civils £8,000 Signals |
2007 | St Saviour’s Road/ Simon’s Place Routine signal replacement and upgrade of pedestrian facilities | Signals need replacement. Pedestrian upgrade in line with current policy established by previous E&PSC. | £20,000 Civils £7,000 Signals |
2007 | Hill Street/ Halkett Place Routine signal replacement and upgrade of pedestrian facilities | Signals need replacement. Pedestrian upgrade in line with current policy established by previous E&PSC. | £18,000 Civils £13,000 Signals |
2007 | Five Oaks Roundabout. On going scheme. | Recent scheme incomplete, and request from the Parish to modify. Trial widened central island and approach islands to be made permanent, power to illuminated bollards required. Work to be carried out during School summer holidays. | £25,000 |
2007 | Central Pedestrian Refuge Island at Miladi Farm, Longueville Road | Pedestrian crossing facility required at Longueville Road. Pedestrian refuge considered the safest solution, which requires road widening and small area of land acquisition, at Miladi Parade. Land acquisition agreed. | £25,000 £10,000 (land acquisition) |
2007 | Beaumont Hill Accident Reduction Scheme | Accident reduction scheme to be designed following road safety audit from filter in turn to mini roundabout at top of hill. More extensive measures to be included in road resurfacing scheme programmed for 2008 | £2,000 |
2007 | Part time 20mph speed limits outside Island Primary Schools | Three schemes programmed for 2007, to trial the principle of part time speed limits outside schools. Trinity, Mont Nicolle and La Moye Schools have been selected for trialling during 2007. | £3,200 |
2007 | Pedestrian Refuge on St Clements Coast Road (Near Avalon) | E&PSC agreed to consider pedestrian refuges, subject to review of effectiveness of those installed on St Aubin’s inner road. | £6,000 |
2007 | Extension of La Rocque Footpath | Willing seller offering to provide land to enable two sections of footpath to be joined, good opportunity to achieve continuous footpath. | £3,000 (plus acquisition of land and accommodation works-£15,000) |
2007 | Green Street Chicanes | Conversion of chicanes from plastic bollards to granite kerb works and permanent bollards, on completion of drainage works in area. | £15,000 |
2007 | Burrard Street Pedestrian Crossing | Installation of raised table zebra crossing with Astucia road studs | £8,800 TTS £12,400POSH |
2007 | Mulcaster Street Pedestrian Crossing | Installation of raised table zebra crossing with belisha beacons | £5,200TTS £13,350POSH |
2007 | Various minor projects | Various minor safety signing and marking schemes as and when required. | £5,000 |