Treasury and Resources
Ministerial Decision Report
Allocation of fiscal stimulus funding for a heating installation Project at the vincent court and albert villa social housing properties
1. Purpose of Report
The tenders for the installation of new heating systems in social housing properties at Vincent Court and Albert Villas have now been received and evaluated by the Housing department. The Tender returns have been subject to review by the Fiscal Stimulus Steering Group (the “Steering Group”) to ensure that the Fiscal Stimulus criteria continue to be met. This paper summarises the resulting recommendation.
2. Background
There are 26 discreet Housing backlog maintenance projects included in the Treasury and Resources Minister’s “amber light” programme of fiscal stimulus projects. The maintenance projects are designed to address deficiencies in meeting standards for decent homes. The work was already planned but without the Discretionary Fiscal Stimulus, it would have had to be delivered over a longer time period in order to meet funding constraints.
All these projects will provide work for local business and labour, and are programmed to be undertaken in 2010 and 2011, significantly increasing public sector spending and investment in Jersey’s infrastructure.
This paper seeks green light approval for the funding of the project set out above.
3. Tender Process and Results
The cost of the project is £185,004.
The housing department has followed a pre-determined process in conducting the tenders which they confirm to be compliant with Financial Directions and Procurement Principles for the Fiscal Stimulus Programme. The process and outcomes have been subject to review by the Steering Group, which has resulted in the recommendation below.
4. Recommendation
Recommendation from the Fiscal Stimulus Steering Group
The Steering Group recommends that the Minister for Treasury and Resources allocates funding of £185,004 to Housing for the project and approves the transfer of that amount to a new capital head of expenditure. The budget allocation to Housing will be in the amount of £185,004, representing the contract costs together with appropriate contingency in order to proceed in accordance with the programme’s critical path.
5. Reason for Decision
A discretionary fiscal stimulus allocation from the Stabilisation Fund of £44m has already been approved. The project meets the key criteria for fiscal stimulus being timely, targeted and temporary and will benefit local business and individuals. The £185,004 allocation to the project will enable the Construction and Maintenance project group to let the contract and deliver the scheme in accordance with the critical path.
6. Resource Implications
No financial resource implications other than those explained above.
No manpower resource implications.
Report author : Acting Fiscal Stimulus Programme Manager | Document date : 30th March 2010 |
Quality Assurance / Review : Business Manager | File name and path: l:\treasury\sections\corporate finance\ministerial decisions\dss, wrs and sds\2010-0055 - fiscal stimulus housing - heating installation - slj\wr - fiscal stimulus housing - heating installation - slj.doc |
MD sponsor : Chief Executive |
Page of 2 Printed: 4/1/2010