Future Hospital expenditure up to 31 December 2018 (FOI)Future Hospital expenditure up to 31 December 2018 (FOI)
Produced by the Freedom of Information officeAuthored by States of Jersey and published on
30 January 2019.Prepared internally, no external costs.
Request
I would like a total breakdown of the £38m that has been spent on the proposed building of the new hospital on its existing site and who has received the money.
Response
Please see table below detailing costs relating to the new hospital up to 31 December 2018.
These figures include accounting accruals for work that has been completed but not yet paid in accordance with States of Jersey accounting principles.
Future Hospital expenditure to 31 December 2018