Nightingale hospital wing costs (FOI)Nightingale hospital wing costs (FOI)
Produced by the Freedom of Information officeAuthored by Government of Jersey and published on
23 July 2021.Prepared internally, no external costs.
Request
A
How much was the initial build cost of the Nightingale Hospital?
B
How much were the running costs and maintenance costs of the Nightingale Hospital from start to finish?
C
How much are the estimated costs of the dismantling of the Nightingale Hospital and field reinstatement?
Response
A
Costs for 2020 have not changed since they were released as part of a previous Freedom of Information (FOI) response, the link to which is as follows:
Track, Trace, Testing, Monitoring and Nightingale costs (FOI)
Costs to the end of June 2021 are £98,488.
B
The costs for 2020 remain at £1,910,886, as previously released in the FOI response below:
Costs relating to the Nightingale Hospital (FOI)
Costs to the end of June 2021 are £1,108,857.
C
The hospital is still in the process of being dismantled. A link to a previous Freedom of Information request detailing estimated costs is below. This information is therefore exempt under Article 23 of the Freedom of Information (Jersey) Law 2011.
Costs associated with the Nightingale Hospital (FOI)
Article applied
Article 23 - Information accessible to applicant by other means
(1) Information is absolutely exempt information if it is reasonably available to the applicant, otherwise than under this Law, whether or not free of charge.
(2) A scheduled public authority that refuses an application for information on this ground must make reasonable efforts to inform the applicant where the applicant may obtain the information.