Our Hospital spend and budget (FOI)Our Hospital spend and budget (FOI)
Produced by the Freedom of Information officeAuthored by Government of Jersey and published on
04 April 2022.Prepared internally, no external costs.
Request
Can you advise
A
How much money has been spent on the new hospital project so far and
B
What the estimated final construction budget is please?
Response
A
The cumulative spend on the Our Hospital Project at the end of February 2022 is £67.9m.
B
The estimated final construction costs of £619.5m are included within the £804.5m budget, as was approved by the States Assembly in October 2021 following a debate on P.80/2021.
P.80/2021, including Appendix 3: The Outline Business Case for Our Hospital, is available on www.gov.je
P.80/2021 (gov.je)