Combined Control Room project costs (FOI)Combined Control Room project costs (FOI)
Produced by the Freedom of Information officeAuthored by Government of Jersey and published on
26 July 2023.Prepared internally, no external costs.
Request
Please advise how much money has been spent, and details of what the money has been spent on, since the start of the combined control room project looking to join up the Police, Fire and Ambulance control room.
This should also include any costs passed on to the project incurred from the Police, Fire and Ambulance services.
Response
The information has been broken down into:
- Professional services, which includes consultancy fees and staff charges.
- Hardware and software.
Pre 2023 |
Professional Services | £572,611.18 |
Hardware and Software | £557,448.18 |
Total | £1,130,059.36 |
2023 |
Professional Services | £259,965.88 |
Hardware and Software | £71,397.48 |
Total | £331,363.36 |
Overall total since inception to the 30 June 2023: £1,461,422.72
This information is based on project costs and does not include ongoing operational costs.