Jersey Airport, Hub2 works and associated funding.
Background
Hub2 is the name given to the equipment room located in the Departure Hall which houses the Tandata system used by airlines and handling agents to record and monitor flight and passenger information. It also houses the infrastructure for flight arrival and departure data which is displayed on the screens in the departure and arrival halls as well as the distribution system for all ‘back of house’ information (Meteorological data, Instrumented Runway Visual Range (IRVR) data, movement & slot times, camera monitors, etc).
The work to be undertaken paves the way for upgrading Hub2 to cope with Voice Over Internet Protocol (VOIP), the Tandata extension currently under way as part of the approved capital programme and the likely introduction of Common Use Terminal Equipment (CUTE)/Customer Use Self Service (CUSS). The area which Hub2 occupies requires enlarging because there is nowhere else in a suitably central location to site the equipment and the current space is insufficient to accommodate the upgrade.
The cost of this enlargement was excluded from the approved capital programme as the equipment was originally to be housed in Hub1 which is now to be decommissioned, a decision taken after the 2008 business plan was approved by the States.
Cost
The total cost including contingency is expected to be no more than £52,000 and can be broken down as follows:-
Preliminaries £ 7,500
Building works & decoration £ 17,850
Air conditioning £ 22,000
Design reserve & contingency £ 3,500
Project contingency £ 1,150
TOTAL £ 52,000
Funding for this project can be met from within the overall approved capital expenditure budget, specifically from the Aeronautical Transmitters & Receivers budget. This project is forecast to cost approximately £125,000 less than budget.
Therefore it is proposed that the £52,000 required for the Hub2 project be transferred into the existing Minor Capital Assets Budget of £300,000 bringing it up to £352,000 and reducing the Aero Tx/Rx budget to £273,000.
Risks
The main risk is that unforeseen expenditure may be required on the Hub2 project once work begins. Although very unlikely it is possible that unforeseen expenditure may be required on the Aero Tx/Rx project. However, every effort will be made to ensure the revised Aero Tx/Rx budget is not exceeded.
D.Mitchell
3 rd April 2008