St. Aubin - Public Realm Master Plan: Procurement of professional services

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made 8 July 2011 regarding:

Decision Reference:  MD-T-2011-0074

Decision Summary Title :

Preparation of a Public Realm Master Plan for St Aubin and the roads in the immediate area.

Date of Decision Summary:

24 June 2011

Decision Summary Author:

 

Acting Senior Engineer

Decision Summary:

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Type of Report:

Oral or Written?

Written

Person Giving

Oral Report:

N/A

Written Report

Title :

Preparation of a Public Realm Master Plan for St Aubin and the roads in the immediate area.

Date of Written Report:

24 June 2011

Written Report Author:

Acting Senior Engineer

Written Report :

Public or Exempt?

(State clauses from Code of Practice booklet)

Public

Subject: Public Realm Master Plan for St Aubin to include the Bulwarks, La Neuve Route and Charing Cross: preparation  - procurement of professional services

 

Decision(s): The Assistant Minister approved the procurement of the professional services required to progress a St Aubin Traffic and Public Realm Master Plan.

 

Reason(s) for Decision: To progress a Traffic and Public Realm Master Plan for St Aubin.

 

Resource Implications: The professional services required to prepare a Public Realm Master Plan can be funded from Departmental funds allocated for the purpose supplemented by a Planning Obligation Agreement from a recent development in the area.

 

Action required: Acting Senior Engineer to procure the professional services of a Highway Engineering Consultant and a Landscape Design Consultant, to prepare the Public Realm Master Plan for St Aubin.

 

Signature:

 

 

Position:

 

 

Date Signed:

 

 

Date of Decision (If different from Date Signed):

 

St. Aubin - Public Realm Master Plan: Procurement of professional services

TRANSPORT AND TECHNICAL SERVICES

 

THE PREPARATION OF A PUBLIC REALM MASTER PLAN FOR ST AUBIN AND

 

ROADS IN THE IMMEDIATE AREA

 

 

 

Purpose of the Report

 

To approve the procurement of professional services to prepare a Public Realm Master Plan for St Aubin to include the Bulwarks, La Neuve Route and Charing Cross.

 

 

Background

 

A number of years ago the Parish of St Aubin held a weekend workshop to discuss and formulate the thoughts and ideas of the community on various issues that had been raised for the area.

 

 

Discussion

 

During the weekend workshop a St Aubin Future Improvement Group was formed from members of the community, which included a sub-group to consider traffic issues called the St Aubin Traffic Advisory Group.

 

The St Aubin Traffic Advisory Group has prepared a summary of ideas and proposals for improvements to the St Aubin area that could be looked into and developed to improve both the operation and aesthetic of the public realm.

 

The Traffic and Public Realm Master Plan will progress the ideas of the community into a master plan that can be progressed over the long term.  While no funding is currently available to carry out physical measures, a master plan will allow various planned maintenance schemes to be carried out within the context of an overall plan. Further funding from other sources such as Planning Obligation Agreements may also become available from time to time.

 

 

Conclusion

 

The Department does not have resources to progress the detailed design of public realm and traffic improvements.  If a master plan is to be progressed then additional professional services support is required.

 

 

 

 

 

 

 

 

 

Recommendation

 

The Assistant Minister is recommended to approve the procurement of the professional services required to progress a St Aubin Traffic and Public Realm Master Plan.

 

Reason(s) for Decision

 

To progress a Traffic and Public Realm Master Plan for St Aubin.

 

 

Resource Implications

 

The professional services required to prepare a Public Realm Master Plan can be funded from Departmental funds allocated for the purpose supplemented by a Planning Obligation Agreement from a recent development in the area.

 

 

Action Required

 

Acting Senior Engineer to procure the professional services of a Highway Engineering Consultant and a Landscape Design Consultant, to prepare the Public Realm Master Plan for St Aubin.

 

 

 

 

 

Written by:

Acting Senior Engineer

 

 

Approved by: 

Director of Transport

 

 

 

I:\Minister\2011\Ministerial Decisions\MD 00 Public Realm Master Plan St Aubin\WR Public Realm Master Plan St Aubin.doc