Les Creux Hotel (formerly known as), Chemin be Beau Port, St. Brelade

A formal published “Ministerial Decision” is required as a record of the decision of a Minister (or an Assistant Minister where they have delegated authority) as they exercise their responsibilities and powers.

Ministers are elected by the States Assembly and have legal responsibilities and powers as “corporation sole” under the States of Jersey Law 2005 by virtue of their office and in their areas of responsibility, including entering into agreements, and under any legislation conferring on them powers.

An accurate record of “Ministerial Decisions” is vital to effective governance, including:

  • demonstrating that good governance, and clear lines of accountability and authority, are in place around decisions-making – including the reasons and basis on which a decision is made, and the action required to implement a decision

  • providing a record of decisions and actions that will be available for examination by States Members, and Panels and Committees of the States Assembly; the public, organisations, and the media; and as a historical record and point of reference for the conduct of public affairs

Ministers are individually accountable to the States Assembly, including for the actions of the departments and agencies which discharge their responsibilities.

The Freedom of Information Law (Jersey) Law 2011 is used as a guide when determining what information is be published. While there is a presumption toward publication to support of transparency and accountability, detailed information may not be published if, for example, it would constitute a breach of data protection, or disclosure would prejudice commercial interest.

A decision made (26.06.07) to grant planning permission to demolish all structures and rebuild on the site formerly known as Les Creux Hotel, Chemin de Beau Port, St. Brelade.

Subject:

(Formerly Known As) Les Creux Hotel, Le Chemin de Beau Port, St. Brelade

Demolish all structures on site. Form 2 No. 5 bed dwellings with associated car parking facilities. Form new access drive to unit 1. ADDITIONAL INFORMATION: Landscaping and woodland management. REVISED PLANS: Internal alterations to existing basement area to create wine cellar and enlarged garage, internal alterations to attic floor. JEC sub station to be created to east.

Decision Reference:

MD-PE-2007-0205

Exempt clause(s):

n/a

Type of Report (oral or written):

Written

Person Giving Report (if oral):

n/a

Telephone or

e-mail Meeting?

n/a

Report

File ref:

RP/2007/0576

Written Report

Title:

Referral to Minister by Officer

Written report – Author:

Andy Townsend

Decision(s)

Grant Planning Permission

Reason(s) for decision:

It was considered that the alterations to the house did not harm its appearance, or dilute the significant improvement of the site achieved by the original approval.

The sub-station was necessary and had been designed to be sympathetic.

Action required:

Notify agent and any interested parties.

Signature:

(Minister)

Date of Decision:

26 June 2007

 

 

 

 

 

Les Creux Hotel (formerly known as), Chemin be Beau Port, St. Brelade

Planning and Environment Department

Planning and Building Services

South Hill

St Helier, Jersey, JE2 4US

Tel: +44 (0)1534 445508

Fax: +44 (0)1534 445528

 

Planning and Environment Department

Report

Application Number

RP/2007/0576

 

Site Address

(Formerly Known As), Les Creux Hotel, Le Chemin de Beau Port, St. Brelade.

 

 

Applicant

Schrecq Developments Limited

 

 

Description

Demolish all structures on site. Form 2 No. 5 bed dwellings with associated car parking facilities. Form new access drive to unit 1. REVISED PLANS: Unit 1 - Internal alterations to existing basement area to create wine cellar and enlarged garage, internal alterations to attic floor. JEC sub station to be created to east.

 

 

Type

Revised Plans

 

 

Date Validated

09/03/2007

 

 

Zones

Zone of Outstanding Character

 

 

Policies

G2 –General Development Considerations

G3 – Quality of Design

C4 – Zone of Outstanding Character

 

 

Reason for Referral

Ministerial Call In

 

Summary/

Conclusion

Planning Permission has already been granted for the construction of two detached houses in place of the unattractive hotel and ancillary buildings.

The alterations to the attic space and basement will not be visible outside the building or have any impact on the apparent scale of the building or its design. These changes will not therefore dilute the environmental improvements achieved when the two houses were originally approved, notwithstanding the increase in floor area.

The substation is required by the JEC, and has to be close to the road. It is to be enclosed by granite walls to match existing. In accordance with officer advice the taller part of the wall is to be extended further towards the north, with the addition of a gate to the enclosure, to better hide the substation structure behind.

 

 

Officer

Recommendation

APPROVE

 

Site Description

Site of former Les Creux Hotel and ancillary buildings directly adjacent to the sea at the western side of St. Brelade’s Bay. The front of the site is very open to view from the bay, but continues into the valley to the rear.

 

 

Relevant Planning History

Planning Permission was granted in June 2006 under reference P/2006/0580 for the redevelopment of the hotel and its outbuildings to create two detached dwellings. The existing buildings were unattractive, and the proposed houses were considered by the Planning Applications Panel to be a considerable environmental improvement. In line with the requirements of Policy C4 in the event of the redevelopment of a commercial site, a reduction in floor area was also achieved, of approximately 30%.

Subsequently a Revised Plans application was submitted to make alterations to Unit 2, the northern unit of a farmhouse based design. This included alterations to the basement level, the addition of a conservatory at ground floor level on the front elevation, and a link between the parallel ridge roof spaces. The application was refused. It was considered that the increase in floor area combined with the design of the extension diluted the quality of the original approval and the environmental benefits achieved.

A further application for more modest changes has now been received but will be dealt with separately.

 

 

Existing use of Land/Buildings

Approved for residential development.

 

 

Proposed use of Land/Buildings

Residential.

 

 

Consultations

T&TS (Drainage) Section – in their comments of 16 March state that their comments remain the same as they were for the original application. Those comments were taken into account at that time, and the application approved. These proposals do not result in any increase in the number of habitable rooms proposed, nor therefore the level of effluent likely to be produced from the property.

The letter is attached with the background papers

 

 

Summary of Representations

2 letters of representation have been received making comments in

regard of:-

  Substation is too exposed and should be relocated.

  No access should be created across countryside towards frequently used public footpaths.

The agent has responded stating that the JEC require a 24 hour access to the substation from a public thoroughfare. The building cannot therefore be located to the rear of the site as is suggested by the objector.

Vehicle access to the site is from the road, and not through the valley to the rear, although a temporary access is required to lay cables.

All letters of representation and responses are attached with the background papers

 

 

Planning Issues

Policy Considerations

The impact of the proposed alterations and the new substation should be considered with regard to Policies G2 (General Development Considerations), G3 (Quality of Design) and C4 (Zone of Outstanding Character.

Land Use Implications

These revisions do not alter the land use which has already been approved.

Size, Scale and Siting

The proposed alterations to the attic area will not be visible from outside the building. They comprise setting the internal walls back further to increase the floorspace. The original approved drawings show the walls positioned at a 2m ceiling height level. The proposal is to push these back to a 1.8m ceiling.

The alterations to the basement and the increase in the size thereof will also not be visible from outside the site. The extension to the basement is westwards towards the rear of the building, and provided the north, west and south elevations are still at the levels originally approved, this work would not be visible once the building is complete.

The agents letter of 2 May and supporting letter from Rothwells explains the construction merits of this given the variable ground conditions.

Policy C4, when considering the redevelopment of commercial sites such as this, also requires a reduction in floor area. The alterations to the attic area and the increase in size of the basement increase the floor area of this proposed unit. This reduces the original loss of floorspace. This is disappointing. However, in assessing the impact of any development Policy C4 states that the key issue will always be the visual impact upon the character of the area. In this particular case these two alterations will not increase the apparent size of this building, or dilute the benefits to the appearance of the site that were achieved by the original Permission and the demolition of the hotel.

The proposed substation is required by the JEC, and by necessity it must be located at the front of the site. To avoid it appearing intrusive the proposals suggest that it would be enclosed in a granite wall to continue and raise the existing roadside granite wall.

Design and Use of Materials

The design of the new house is not changed, nor the use of external materials.

Substation – See Size, Scale and Siting above.

Impact on Neighbours

Neither the proposed alterations to the house nor the substation will have any material impact on any adjoining property, each neighbour being reasonably distant from the substation.

Access, Car parking and Highway Considerations

Note relevant – no changes to parking requirements or access.

Foul Sewage Disposal

Site relies upon a septic tank and soakaway, but this arrangement was approved as part of the original scheme as it was considered that two houses would significantly reduce the drainage output of the site from the existing hotel and outbuildings. The alterations now proposed do not increase the occupancy of the buildings or therefore the drainage loading.

Landscaping issues

See Size, Scale and Siting above.

Other Material Considerations

None relevant to the determination of this application.

 

 

Officer

Recommendation

APPROVE

 

 

Conditions/

Reasons

1. The attic area enlarged in this application shall not be subdivided to create more than one room, which would increase the drainage loading of the site.

 

 

Background Papers

1:2500 Location Plan

2 letters of objection.

Applicant’s letters 28 March,11 April and 2 May

Consultation response from Transport and Technical Services (Drainage).

 

Endorsed by:

 

Date:

19 June 2007

 

 

Back to top