16 September 2015
Work to stabilise the rock face above Snow Hill car park will begin on Monday 21 September.
The essential works to the area above the ‘concrete catcher’ is the final part a wider project commissioned by Jersey Property Holdings to support the Fort Regent rock faces. The high risk areas for work had been highlighted in a detailed structural survey carried out in 2011.
During different phases of the work, areas of the Snow Hill car park will be closed to ensure public safety but pedestrian footpath access and access to the motorbike and bicycle parking areas at Hill Street /Snow Hill will be maintained throughout the work.
Work suspended over Christmas
With the agreement of the Transport and Technical Services Department (TTS) the work will be suspended over the Christmas period so that short stay shopper parking will not be disrupted. Unavailable spaces will be cordoned off.
Jersey Property Holdings have awarded the contract for the work to local company Geomarine Ltd.
Transport and Technical Services Minister and Assistant Treasury Minister with responsibility for Jersey Property Holdings, Deputy Eddie Noel, said “The final stage of this project will ensure the long term stability of the rock face around Fort Regent and ensure the safety of the public using Snow Hill car park. We are pleased to be able to award the contract for this work to a local company through a competitive tendering process.”
Phase One
Location | Area nearest the motorbike parking |
Number of parking spaces unavailable | 20 |
Start date | Monday 21 September 2015 |
End date | Thursday 5 November 2015 |
Duration | Seven weeks |
Phase Two
Location | Middle section of rockface |
Number of spaces unavailable | 28 |
Start date | Friday 6 November 2015 |
Work suspended for Christmas shoppers | Monday 30 November 2015 to Monday 4 January 2016 |
End date | Friday 22 January 2016 |
Duration | Six weeks |
Phase Three
Location | Entrance of car park section of rock face |
Number of parking spaces unavailable | 33 |
Start date | Monday 25 January 2016 |
End date | Friday 4 March 2016 |
Duration | Six weeks |