About the project
As part of the ongoing highway maintenance by Infrastructure and Environment, the Esplanade’s carriageway is being reconstructed between the junction with Gloucester Street and the junction with Peirson Road.
The project is split into 4 sections and each section will be constructed during the school holidays. To minimise the disruption to traffic 2 lanes in each direction will remain open during the project.
We will implement a contra-flow system and provide diversions within the local area. The contra-flow system will be implemented and will remain in place 24 hours a day for the duration of the project.
Esplanade Phase 4: October 2024
The Esplanade is a strategic route so to minimise the disruption to traffic 2-lanes in each direction will remain open during the project.
To do the carriageway reconstruction works we'll implement a contra-flow system and also provide a number of diversions within the local area. The contra-flow system will be implemented and will remain in place 24 hours a day for the duration of the project.
Schedule of work for Phase 4
Work will take place on Section 3: Lane 3, half of lane 2 of eastbound carriageway from Saturday 26 October to Sunday 3 November.
Area of work and working hours
The area of work will be Lane 3 and half of lane 2 of the Esplanade eastbound carriageway between Peirson Road and Gloucester Street.
Phase 4 area of work map
Monday to Friday
| 7.30am to 9pm
|
---|
Saturday and Sunday
| 9am to 9pm
|
---|
Diversion route
All traffic is prohibited from turning right from the Esplanades westbound carriageway onto Kensington Place, Peirson Road, or to Westpark roundabout. This includes St Aubin's inner road westbound and northbound toward the parade.
The diversion for these roads is along Victoria Avenue to First Tower, a right turn onto la Route de St Aubin (St Aubin's inner road eastbound) to Westpark roundabout:
- divert left at Westpark roundabout for Cheapside, The Parade and Gloucester Street
- for Kensington Place and Peirson Road the diversion returns to the esplanade eastbound with left turns permitted
Diversion route 1 map (Kensington Place diversion)
Travelling to the Hospital and Patriotic Street car park
Allow additional time to get to the hospital during the work as delays are expected.
Access to Hospital and Patriotic Street car park is maintained with 1 diversion for route for access from the east. These routes to be used are:
From the west
Option 1 is via la Route de St Aubin (Inner Road), St Aubin’s Road, Peirson Road, Cheapside, The Parade and Gloucester Street.
Option 2 is via Victoria Avenue, Peirson Road, Cheapside, The Parade and Gloucester Street.
From the east
La Route de la Liberation, Castle Street, Rue des Mielles and Seaton Place. This is shown in Diversion Route 2 below.
The diversion route to Patriotic Street car park and the General Hospital when coming from the east is Route du Fort, Route de la Liberation, Castle Street roundabout, Castle Street, Esplanade, Anley Street, Seaton Place, Patriotic Place.
Diversion Route 2 map (Patriotic Street Car Park diversion)
Access to businesses
Access to businesses will be as usual, to access Kensington place from the east please use the diversion by First Tower.
Buses
There are minor disruptions to the bus service, for more information can be found on Tower Transport.
Schedule of work for all sections
Section 1 (completed)
| Completed October half term 2021
| Lane 1 and half of lane 2 westbound carriageway
|
---|
Section 2 (completed)
| Completed October half term 2023
| Lane 3, half of lane 2 and right turn lanes westbound carriageway
|
---|
Section 3
| 26 October to 3 November 2024
| Lane 3 and half of lane 2 eastbound carriageway
|
---|
Section 4 (completed)
| Completed October half term 2022
| Lane 1 and half of lane 2 eastbound carriageway
|
---|